Supplier Quality - Containment & Corrective Action
Problem Statements
- Screws specific to latching applications were failing without warning
- Potential for customer down time in the field
- Potential assembly down time
- 18 week lead time on internationally procured screw with 3/4 million annual usage
Solution
- Facilitated cross functional root cause investigation meetings with design, quality, supplier management and screw vendor
- Participated in Root Cause Analysis which included mechanical testing to identify Hydrogen Embrittlement as cause of failure
- Facilitated the quarantine and disposal of all suspect nonconforming material
- Created short term field modification procedures
- Lead team in setting up procurement of the screw from a previous domestic supplier
- Communicated with the supplier and defined the PPAP requirements for all future material
Results
- No customers with down time in the field as short term corrective action was implemented prior to delivery of product from dealerships
- Assembly downtime was negated due to quick ramp up of domestic supplier
- Fully defined quality inspection plan was put in place along with testing to prevent future Hydrogen Embrittlement issues.
|
|